CASE STUDY UROS-CT is the solution for close tolerance offshore well in Senegal
THE CHALLENGE
To provide a configuration for a 291ft liner with Baker Hughes inline liner hanger and 11 ¾” 65ppg and P110 Wedge 513 casing. Centralizers to be run inside a 13 3/8” 72ppf P110 Vam Top casing with an ID of 12.347” with a drift of 12.191”.
THE SOLUTION
The customer ran 10 x 11 3/4-14 3/4 UROS CT centralizers with ACE Ratchet collars on the 291m liner.
THE RESULT
The minimum pass through of the UROS-CT is 12.347” and the customer encountered no issues.