CASE STUDY Centek S2 centralizers halve the time to get to bottom
THE CHALLENGE
To improve running casing time in this 16,695ft well in the lower Wolfscamp shale, Reeves Country, Texas. This normally takes around 30-35 hours.
THE SOLUTION
187 x Centek S2 centralizers with 374 Centek stop collars were used on a string of 420 joints.
THE RESULT
The whole job ran in only 16.5 hours, even with the centralizers and stop collars being fitted on the rig floor. In this 8.1/2”
open hole, that’s 2.36 minutes per joint, fitted.